Question 1. Question
: (TCO 1) A project is defined
as a(n) _____ endeavor undertaken to create a(n) _____ product, service, or
result.

challenging; new

temporary; unique

new; challenging

ongoing; unique

Question 2. Question
: (TCO 1) Which document on a
project authorizes the project manager to begin work on the project?

The scope

The schedule

The charter

The risk management plan

Question 3. Question
: (TCO 2) Project deliverables
are created in the _____ , which is completed during the _____ phase of a
project.

charter; execution

scope; planning

schedule; planning

charter; planning

Week
2 Lecture

Comments:

Question 4. Question
: (TCO 2) Which statement is an
example of a project assumption?

“If the parts arrive late, we will not finish
on time.”

“We must get permits before we start work.”

“I believe the contracts will be signed by the
15th.”

“The paving of the parking lot will be
completed within this project.”

Week
2 Lecture

Comments:

Question 5. Question
: (TCO 3) The amount of time an
activity can be delayed without impacting the end date of the project is known
as what?

Project risk

Slack

Critical path

Early start

Chapter
9

5
of 5
Comments:

Question 6. Question
: (TCO 3) What values are
calculated on the backward pass of a project network?

Early start; late start

Early start; early finish

Late start; late finish

Early finish; late finish

Chapter
9

Comments:

Question 7. Question
: (TCO 5) In which process of
risk management is the risk register initially created?

Plan risk management

Identify risks

Control risks

Qualitative risk analysis

Week
4 Lecture

5
of 5
Comments:

Question 8. Question
: (TCO 5) Contingency plans are
created

to proactively address the risk.

to respond to the risk should the risk occur.

to gather information on vital risks.

to avoid red risks in the project plan .

Week
4 Lecture

Comments:

Page: 1
2

Question 1. Question
: (TCO 1) Before one can begin
writing a charter, one must consider the most appropriate organization for the
project. You are the project manager for a company that integrates custom data
solutions for large corporate enterprises. This project will span two or three
years and will cost tens of millions of dollars. This is a large, very involved
project. Which of the five organization structures is most suitable? Why?

Question 2. Question
: (TCO 2) You are a project
manager for a new hardware/software project. You just received the project
charter and established your scope statement. Within the scope statement, you
defined some of the key components to meet the overall project objective.
Establishing requirements will be critical to define and get approved. The
hardware will be new for your company, so you will need to ensure the vendor is
selected and the hardware is appropriately installed into your environment. The
supporting software will need to be designed and coded. It will also need to be
installed and tested on the system. To ensure the users know how to use the new
software, training will be needed for managers and the associates. You have
assembled your team of experts and they are anxious to get started.

Part 1: To ensure you have a clear scope for your team,
create a 2-level WBS. Don’t forget to include your WBS numbering. (15 points)

Part 2: In your WBS, how many work packages have been
created? (5 points)

:

Question 3. Question
: (TCO 3) Compare and contrast
fast tracking and scope reduction as means of schedule compression.

Question 4. Question
: (TCO 5) A firm hosts
data-mining servers and performs data mining for other companies that do not
desire the costs of hardware, software, or expertise to data mine their data.
The firm is planning to roll out faster data-mining software that will reduce
the time to sift through customers’ data by a fraction of the present time.

Part 1: List and discuss the major risk management functions
from a project management perspective for the data-mining software project. (15
points)

Part 2: Describe a positive and negative risk event, the
consequences, and the risk-response plans for the data-mining software project.
(15 points)

Question 5. Question
: (TCO 9) Compare and contrast
the development of a WBS in traditional project management versus development
in an agile environment.

Page: 1
2

Question 1. Question
: (TCO 1) A project is defined
as a(n) _____ endeavor undertaken to create a(n) _____ product, service, or
result.

challenging; new

temporary; unique

new; challenging

ongoing; unique

Question 2. Question
: (TCO 1) Which document on a
project authorizes the project manager to begin work on the project?

The scope

The schedule

The charter

The risk management plan

Question 3. Question
: (TCO 2) Project deliverables
are created in the _____ , which is completed during the _____ phase of a
project.

charter; execution

scope; planning

schedule; planning

charter; planning

Week
2 Lecture

Comments:

Question 4. Question
: (TCO 2) Which statement is an
example of a project assumption?

“If the parts arrive late, we will not finish
on time.”

“We must get permits before we start work.”

“I believe the contracts will be signed by the
15th.”

“The paving of the parking lot will be
completed within this project.”

Week
2 Lecture

Comments:

Question 5. Question
: (TCO 3) The amount of time an
activity can be delayed without impacting the end date of the project is known
as what?

Project risk

Slack

Critical path

Early start

Chapter
9

5
of 5
Comments:

Question 6. Question
: (TCO 3) What values are
calculated on the backward pass of a project network?

Early start; late start

Early start; early finish

Late start; late finish

Early finish; late finish

Chapter
9

Comments:

Question 7. Question
: (TCO 5) In which process of
risk management is the risk register initially created?

Plan risk management

Identify risks

Control risks

Qualitative risk analysis

Week
4 Lecture

5
of 5
Comments:

Question 8. Question
: (TCO 5) Contingency plans are
created

to proactively address the risk.

to respond to the risk should the risk occur.

to gather information on vital risks.

to avoid red risks in the project plan .

Week
4 Lecture

Comments:

Page: 1
2

Question 1. Question
: (TCO 1) Before one can begin
writing a charter, one must consider the most appropriate organization for the
project. You are the project manager for a company that integrates custom data
solutions for large corporate enterprises. This project will span two or three
years and will cost tens of millions of dollars. This is a large, very involved
project. Which of the five organization structures is most suitable? Why?

Question 2. Question
: (TCO 2) You are a project
manager for a new hardware/software project. You just received the project
charter and established your scope statement. Within the scope statement, you
defined some of the key components to meet the overall project objective.
Establishing requirements will be critical to define and get approved. The
hardware will be new for your company, so you will need to ensure the vendor is
selected and the hardware is appropriately installed into your environment. The
supporting software will need to be designed and coded. It will also need to be
installed and tested on the system. To ensure the users know how to use the new
software, training will be needed for managers and the associates. You have
assembled your team of experts and they are anxious to get started.

Part 1: To ensure you have a clear scope for your team,
create a 2-level WBS. Don’t forget to include your WBS numbering. (15 points)

Part 2: In your WBS, how many work packages have been
created? (5 points)

:

Question 3. Question
: (TCO 3) Compare and contrast
fast tracking and scope reduction as means of schedule compression.

Question 4. Question
: (TCO 5) A firm hosts
data-mining servers and performs data mining for other companies that do not
desire the costs of hardware, software, or expertise to data mine their data.
The firm is planning to roll out faster data-mining software that will reduce
the time to sift through customers’ data by a fraction of the present time.

Part 1: List and discuss the major risk management functions
from a project management perspective for the data-mining software project. (15
points)

Part 2: Describe a positive and negative risk event, the
consequences, and the risk-response plans for the data-mining software project.
(15 points)

Question 5. Question
: (TCO 9) Compare and contrast
the development of a WBS in traditional project management versus development
in an agile environment.

Page: 1
2

Question 1. Question
: (TCO 1) A project is defined
as a(n) _____ endeavor undertaken to create a(n) _____ product, service, or
result.

challenging; new

temporary; unique

new; challenging

ongoing; unique

Question 2. Question
: (TCO 1) Which document on a
project authorizes the project manager to begin work on the project?

The scope

The schedule

The charter

The risk management plan

Question 3. Question
: (TCO 2) Project deliverables
are created in the _____ , which is completed during the _____ phase of a
project.

charter; execution

scope; planning

schedule; planning

charter; planning

Week
2 Lecture

Comments:

Question 4. Question
: (TCO 2) Which statement is an
example of a project assumption?

“If the parts arrive late, we will not finish
on time.”

“We must get permits before we start work.”

“I believe the contracts will be signed by the
15th.”

“The paving of the parking lot will be
completed within this project.”

Week
2 Lecture

Comments:

Question 5. Question
: (TCO 3) The amount of time an
activity can be delayed without impacting the end date of the project is known
as what?

Project risk

Slack

Critical path

Early start

Chapter
9

5
of 5
Comments:

Question 6. Question
: (TCO 3) What values are
calculated on the backward pass of a project network?

Early start; late start

Early start; early finish

Late start; late finish

Early finish; late finish

Chapter
9

Comments:

Question 7. Question
: (TCO 5) In which process of
risk management is the risk register initially created?

Plan risk management

Identify risks

Control risks

Qualitative risk analysis

Week
4 Lecture

5
of 5
Comments:

Question 8. Question
: (TCO 5) Contingency plans are
created

to proactively address the risk.

to respond to the risk should the risk occur.

to gather information on vital risks.

to avoid red risks in the project plan .

Week
4 Lecture

Comments:

Page: 1
2

Question 1. Question
: (TCO 1) Before one can begin
writing a charter, one must consider the most appropriate organization for the
project. You are the project manager for a company that integrates custom data
solutions for large corporate enterprises. This project will span two or three
years and will cost tens of millions of dollars. This is a large, very involved
project. Which of the five organization structures is most suitable? Why?

Question 2. Question
: (TCO 2) You are a project
manager for a new hardware/software project. You just received the project
charter and established your scope statement. Within the scope statement, you
defined some of the key components to meet the overall project objective.
Establishing requirements will be critical to define and get approved. The
hardware will be new for your company, so you will need to ensure the vendor is
selected and the hardware is appropriately installed into your environment. The
supporting software will need to be designed and coded. It will also need to be
installed and tested on the system. To ensure the users know how to use the new
software, training will be needed for managers and the associates. You have
assembled your team of experts and they are anxious to get started.

Part 1: To ensure you have a clear scope for your team,
create a 2-level WBS. Don’t forget to include your WBS numbering. (15 points)

Part 2: In your WBS, how many work packages have been
created? (5 points)

:

Question 3. Question
: (TCO 3) Compare and contrast
fast tracking and scope reduction as means of schedule compression.

Question 4. Question
: (TCO 5) A firm hosts
data-mining servers and performs data mining for other companies that do not
desire the costs of hardware, software, or expertise to data mine their data.
The firm is planning to roll out faster data-mining software that will reduce
the time to sift through customers’ data by a fraction of the present time.

Part 1: List and discuss the major risk management functions
from a project management perspective for the data-mining software project. (15
points)

Part 2: Describe a positive and negative risk event, the
consequences, and the risk-response plans for the data-mining software project.
(15 points)

Question 5. Question
: (TCO 9) Compare and contrast
the development of a WBS in traditional project management versus development
in an agile environment.

Page: 1
2


Question 1. Question
: (TCO 1) A project is defined
as a(n) _____ endeavor undertaken to create a(n) _____ product, service, or
result.




challenging; new

temporary; unique

new; challenging

ongoing; unique

Question 2. Question
: (TCO 1) Which document on a
project authorizes the project manager to begin work on the project?



The scope

The schedule

The charter

The risk management plan

Question 3. Question
: (TCO 2) Project deliverables
are created in the _____ , which is completed during the _____ phase of a
project.




charter; execution

scope; planning

schedule; planning

charter; planning

Week
2 Lecture


Comments:

Question 4. Question
: (TCO 2) Which statement is an
example of a project assumption?



“If the parts arrive late, we will not finish
on time.”


“We must get permits before we start work.”

“I believe the contracts will be signed by the
15th.”


“The paving of the parking lot will be
completed within this project.”


Week
2 Lecture


Comments:

Question 5. Question
: (TCO 3) The amount of time an
activity can be delayed without impacting the end date of the project is known
as what?




Project risk

Slack

Critical path

Early start

Chapter
9


5
of 5
Comments:



Question 6. Question
: (TCO 3) What values are
calculated on the backward pass of a project network?



Early start; late start

Early start; early finish

Late start; late finish

Early finish; late finish

Chapter
9


Comments:

Question 7. Question
: (TCO 5) In which process of
risk management is the risk register initially created?



Plan risk management

Identify risks

Control risks

Qualitative risk analysis

Week
4 Lecture


5
of 5
Comments:



Question 8. Question
: (TCO 5) Contingency plans are
created



to proactively address the risk.

to respond to the risk should the risk occur.

to gather information on vital risks.

to avoid red risks in the project plan .

Week
4 Lecture


Comments:

Page: 1
2


Question 1. Question
: (TCO 1) Before one can begin
writing a charter, one must consider the most appropriate organization for the
project. You are the project manager for a company that integrates custom data
solutions for large corporate enterprises. This project will span two or three
years and will cost tens of millions of dollars. This is a large, very involved
project. Which of the five organization structures is most suitable? Why?







Question 2. Question
: (TCO 2) You are a project
manager for a new hardware/software project. You just received the project
charter and established your scope statement. Within the scope statement, you
defined some of the key components to meet the overall project objective.
Establishing requirements will be critical to define and get approved. The
hardware will be new for your company, so you will need to ensure the vendor is
selected and the hardware is appropriately installed into your environment. The
supporting software will need to be designed and coded. It will also need to be
installed and tested on the system. To ensure the users know how to use the new
software, training will be needed for managers and the associates. You have
assembled your team of experts and they are anxious to get started.












Part 1: To ensure you have a clear scope for your team,
create a 2-level WBS. Don’t forget to include your WBS numbering. (15 points)


Part 2: In your WBS, how many work packages have been
created? (5 points)


:

Question 3. Question
: (TCO 3) Compare and contrast
fast tracking and scope reduction as means of schedule compression.



Question 4. Question
: (TCO 5) A firm hosts
data-mining servers and performs data mining for other companies that do not
desire the costs of hardware, software, or expertise to data mine their data.
The firm is planning to roll out faster data-mining software that will reduce
the time to sift through customers’ data by a fraction of the present time.






Part 1: List and discuss the major risk management functions
from a project management perspective for the data-mining software project. (15
points)



Part 2: Describe a positive and negative risk event, the
consequences, and the risk-response plans for the data-mining software project.
(15 points)



Question 5. Question
: (TCO 9) Compare and contrast
the development of a WBS in traditional project management versus development
in an agile environment.




testimonials icon
1Running head: OUR KIDS: THE AMERICAN DREAM IN CRISIS AN ANALYTICALREFLECTIONOur Kids: The American Dream in Crisis An Analytical ReflectionName:Inst...
testimonials icon
This assignment is on GED 155 English essay #4 . In what ways does having a company website provide custom...
testimonials icon
How would you use nursing theory to improve or evaluate the quality of clinical practice?Needs to be in correct APA format and this include...
testimonials icon
please respond to Mary the following with 150 words:Hello my name is Mary White, I actually go by Liz. I am 57 years old, married w...
testimonials icon
Reply to the following 2 post in 100 words or more each. Compensation posted by Rosie Cordova , Apr 30, 2018,...
testimonials icon
 Research your state’s law, or a state in which you are familiar, on protective orders and identify who is covered and w...
testimonials icon
Forum Topic Responses: One comprehensive forum topic response is assigned weekly. Students are required to select and re...
testimonials icon
Running Head: ARTICLE REVIEW1An Article Review: A Comprehensive Survey of Security Issues and Defense Frameworkfor VoIP CloudAuthorInstitutional Affi...
testimonials icon
Introduce yourself, why are you interested in taking the course?  What do you hope to learn from it?  What do you identify with in C. S....
testimonials icon
Paper View Plain Text View...

Other samples, services and questions:

Calculate Price

When you use PaperHelp, you save one valuable — TIME

You can spend it for more important things than paper writing.

Approx. price
$65
Order a paper. Study better. Sleep tight. Calculate Price!
Created with Sketch.
Calculate Price
Approx. price
$65