BUSI 313 Quiz 2 Liberty University Complete Answers
Question 1 A typical responsibility matrix will include not
only those responsible for a specific task but can also include
those who supply support and assistance.
Question 2 Integrating a project’s work packages within the
organization’s management structure is known as work breakdown
structure.
Question 3 If the project time should be accepted, then the
project must be completed on time.
Question 4 In reviewing the project plan, Susan sees that the
first prototype must be completed by October 12. This would be best
classified as a
Question 5 Which of the following is a good example of a
Process Breakdown Structure?
Question 6 There are 5 steps involved when defining a
project? which of the following is the first?
Question 7 The final stage in defining a project is coding
the organization breakdown structure or OBS for the information
system.
Question 8 For large companies, the organization breakdown
structure is used rather than the work breakdown structure.
Question 9 The highest element in the hierarchical breakdown
of the WBS is the first major deliverable for the project and the
lowest element is a work package.
Question 10 Accounting would be an example of which of the
following costs typically found in a project?
Question 11 Estimates are supposed to be based on normal
conditions. While this is a good starting point, it rarely holds
true in real life.
Question 12 Cost, time, and budget estimates are the lifeline
for control? they serve as the standard for comparison of the
actual and the planned throughout the life of the project.
Question 13 Refining estimates may be necessary for a number
of reasons. For example, people working on prototype development
needing time to interact with the design engineers after the design
is completed is a good example of
Question 14 A good starting point for developing time and
cost estimates is
Question 18 The requirement for a freshly poured foundation
to cure before beginning construction is an example of which of the
following type of lag?
Question 19 Tom is responsible for ordering hardware for a
custom home his company is building. The contractor installing the
hardware is scheduled to start in 5 working days, but the hardware
is on backorder and will not arrive for another 9 working days.
Fortunately, Tom has 10 days of slack? however, he shares this
slack with the hardware installer. He will have to let the
contactor know that the hardware will be ready 4 days later than
expected and that the slack for the installer has been reduced by 4
days. Tom and the installer share 10 days of
Question 20 The critical path is the shortest path through a
network and indicates activities that cannot be delayed without
delaying the project.
Question 21 Which of the following will correctly calculate
the total slack in an activity?
Question 22 A merge activity is one that merges with other
activities into a succeeding activity.
Question 23 Different activities along the same path can have
different total slack.
Question 24 It is acceptable for arrows to cross one another
in a network diagram.
Question 25 Which of the following can be used without
coordinating with managers of succeeding activities?
BUSI 313 Quiz 2 Liberty University Complete Answers
Question 1 A typical responsibility matrix will include not
only those responsible for a specific task but can also include
those who supply support and assistance.
Question 2 Integrating a project’s work packages within the
organization’s management structure is known as work breakdown
structure.
Question 3 If the project time should be accepted, then the
project must be completed on time.
Question 4 In reviewing the project plan, Susan sees that the
first prototype must be completed by October 12. This would be best
classified as a
Question 5 Which of the following is a good example of a
Process Breakdown Structure?
Question 6 There are 5 steps involved when defining a
project? which of the following is the first?
Question 7 The final stage in defining a project is coding
the organization breakdown structure or OBS for the information
system.
Question 8 For large companies, the organization breakdown
structure is used rather than the work breakdown structure.
Question 9 The highest element in the hierarchical breakdown
of the WBS is the first major deliverable for the project and the
lowest element is a work package.
Question 10 Accounting would be an example of which of the
following costs typically found in a project?
Question 11 Estimates are supposed to be based on normal
conditions. While this is a good starting point, it rarely holds
true in real life.
Question 12 Cost, time, and budget estimates are the lifeline
for control? they serve as the standard for comparison of the
actual and the planned throughout the life of the project.
Question 13 Refining estimates may be necessary for a number
of reasons. For example, people working on prototype development
needing time to interact with the design engineers after the design
is completed is a good example of
Question 14 A good starting point for developing time and
cost estimates is
Question 18 The requirement for a freshly poured foundation
to cure before beginning construction is an example of which of the
following type of lag?
Question 19 Tom is responsible for ordering hardware for a
custom home his company is building. The contractor installing the
hardware is scheduled to start in 5 working days, but the hardware
is on backorder and will not arrive for another 9 working days.
Fortunately, Tom has 10 days of slack? however, he shares this
slack with the hardware installer. He will have to let the
contactor know that the hardware will be ready 4 days later than
expected and that the slack for the installer has been reduced by 4
days. Tom and the installer share 10 days of
Question 20 The critical path is the shortest path through a
network and indicates activities that cannot be delayed without
delaying the project.
Question 21 Which of the following will correctly calculate
the total slack in an activity?
Question 22 A merge activity is one that merges with other
activities into a succeeding activity.
Question 23 Different activities along the same path can have
different total slack.
Question 24 It is acceptable for arrows to cross one another
in a network diagram.
Question 25 Which of the following can be used without
coordinating with managers of succeeding activities?
BUSI 313 Quiz 2 Liberty University Complete Answers
Question 1 A typical responsibility matrix will include not
only those responsible for a specific task but can also include
those who supply support and assistance.
Question 2 Integrating a project’s work packages within the
organization’s management structure is known as work breakdown
structure.
Question 3 If the project time should be accepted, then the
project must be completed on time.
Question 4 In reviewing the project plan, Susan sees that the
first prototype must be completed by October 12. This would be best
classified as a
Question 5 Which of the following is a good example of a
Process Breakdown Structure?
Question 6 There are 5 steps involved when defining a
project? which of the following is the first?
Question 7 The final stage in defining a project is coding
the organization breakdown structure or OBS for the information
system.
Question 8 For large companies, the organization breakdown
structure is used rather than the work breakdown structure.
Question 9 The highest element in the hierarchical breakdown
of the WBS is the first major deliverable for the project and the
lowest element is a work package.
Question 10 Accounting would be an example of which of the
following costs typically found in a project?
Question 11 Estimates are supposed to be based on normal
conditions. While this is a good starting point, it rarely holds
true in real life.
Question 12 Cost, time, and budget estimates are the lifeline
for control? they serve as the standard for comparison of the
actual and the planned throughout the life of the project.
Question 13 Refining estimates may be necessary for a number
of reasons. For example, people working on prototype development
needing time to interact with the design engineers after the design
is completed is a good example of
Question 14 A good starting point for developing time and
cost estimates is
Question 18 The requirement for a freshly poured foundation
to cure before beginning construction is an example of which of the
following type of lag?
Question 19 Tom is responsible for ordering hardware for a
custom home his company is building. The contractor installing the
hardware is scheduled to start in 5 working days, but the hardware
is on backorder and will not arrive for another 9 working days.
Fortunately, Tom has 10 days of slack? however, he shares this
slack with the hardware installer. He will have to let the
contactor know that the hardware will be ready 4 days later than
expected and that the slack for the installer has been reduced by 4
days. Tom and the installer share 10 days of
Question 20 The critical path is the shortest path through a
network and indicates activities that cannot be delayed without
delaying the project.
Question 21 Which of the following will correctly calculate
the total slack in an activity?
Question 22 A merge activity is one that merges with other
activities into a succeeding activity.
Question 23 Different activities along the same path can have
different total slack.
Question 24 It is acceptable for arrows to cross one another
in a network diagram.
Question 25 Which of the following can be used without
coordinating with managers of succeeding activities?
BUSI 313 Quiz 2 Liberty University Complete Answers
Question 1 A typical responsibility matrix will include not
only those responsible for a specific task but can also include
those who supply support and assistance.
Question 2 Integrating a project’s work packages within the
organization’s management structure is known as work breakdown
structure.
Question 3 If the project time should be accepted, then the
project must be completed on time.
Question 4 In reviewing the project plan, Susan sees that the
first prototype must be completed by October 12. This would be best
classified as a
Question 5 Which of the following is a good example of a
Process Breakdown Structure?
Question 6 There are 5 steps involved when defining a
project? which of the following is the first?
Question 7 The final stage in defining a project is coding
the organization breakdown structure or OBS for the information
system.
Question 8 For large companies, the organization breakdown
structure is used rather than the work breakdown structure.
Question 9 The highest element in the hierarchical breakdown
of the WBS is the first major deliverable for the project and the
lowest element is a work package.
Question 10 Accounting would be an example of which of the
following costs typically found in a project?
Question 11 Estimates are supposed to be based on normal
conditions. While this is a good starting point, it rarely holds
true in real life.
Question 12 Cost, time, and budget estimates are the lifeline
for control? they serve as the standard for comparison of the
actual and the planned throughout the life of the project.
Question 13 Refining estimates may be necessary for a number
of reasons. For example, people working on prototype development
needing time to interact with the design engineers after the design
is completed is a good example of
Question 14 A good starting point for developing time and
cost estimates is
Question 18 The requirement for a freshly poured foundation
to cure before beginning construction is an example of which of the
following type of lag?
Question 19 Tom is responsible for ordering hardware for a
custom home his company is building. The contractor installing the
hardware is scheduled to start in 5 working days, but the hardware
is on backorder and will not arrive for another 9 working days.
Fortunately, Tom has 10 days of slack? however, he shares this
slack with the hardware installer. He will have to let the
contactor know that the hardware will be ready 4 days later than
expected and that the slack for the installer has been reduced by 4
days. Tom and the installer share 10 days of
Question 20 The critical path is the shortest path through a
network and indicates activities that cannot be delayed without
delaying the project.
Question 21 Which of the following will correctly calculate
the total slack in an activity?
Question 22 A merge activity is one that merges with other
activities into a succeeding activity.
Question 23 Different activities along the same path can have
different total slack.
Question 24 It is acceptable for arrows to cross one another
in a network diagram.
Question 25 Which of the following can be used without
coordinating with managers of succeeding activities?